The Department of Public Works, DOW, announces to the community in general that this week several roads will be closed for repair works.

Monday, February 21, 2011:  

  • Reconstruction works starts in Paradera on the road in front of the old AAA building, from Paradera # 75A until Paradera # 79. Duration: 15 working days.
  • Laurens Costerstraat will be recapped from the crossing with the La Sallestraat until Laurens Costersraat # 15 Duration: app. 20 working days.
  • Part of the roundabout at Bakval will be closed to put asphalt on a piece of remaining dirt road. There will be no traffic going direction south, only going north direction Malmok, while traffic coming from Malmok going south must make a turn direction Bakval.

Tuesday. February 22, 2011:

  • Reconstruction work of Newtonstraat starling at Newtonstraat 1 until Newtonstraat # 19. Duration: 20 working days.
  • Asphalting of the road Barcadera-Rooi Bosal starting at the crossing Rooi Basal/Barcadera direction POVA Club up to the crossing nest to Barcadera 23, Duration: app. 40 working days.
  • Asphalting Phase I of Topaz road from the crossing of Caya Francisco Figaroa up to Topaz # 59. Duration: 20 working days.

Wednesday, February23, 2011:

  • Asphalting of the Macuarima road, from the Macuarirna preparatory school until Macuarima # 23. Duration: 25 working days.

Motorists are kindly requested NOT to use these roads unless to go home or the office. All the roads will be closed for both directions from 7:00 am, until 4:00 pm. There will be barricades and traffic signs advising motorists. DOW asks for the publics understanding and apologizes for any inconvenience these works may cause.